CrossrailAmalgamation of Tunnel Secondary Lining and First Stage Concrete at Whitechapel Crossover
Summary
After completion of primary lining construction for the Whitechapel Crossover, a value engineering exercise was undertaken to save time within the overall construction programme and Crossrail’s overall critical path for the completion of the tunnels, platform tunnel fit out and construction of track-slab through the station. Savings of approximately 2 months and £1M were identified by amalgamating the first stage track bed (FSC) and tunnel secondary lining invert, constructed by C510 station in order to relieve the programmes of follow-on construction. The proposal was designed by C121 and is being constructed by C510 Whitechapel and Liverpool Street Station Tunnels. This paper describes the resulting unusual design and construction issues.
The structure comprises primary lining, secondary lining, FSC and second stage track bed (SSC). If space and interface requirements are well defined, these can be designed independently. On the interface between the primary and secondary lining there is a waterproofing system. On the interface between secondary lining and FSC was a pressure relief drainage system (PRD). Amalgamation of the secondary lining invert and FSC changed this arrangement.
The invert became thicker, less round and required structural and anti-cracking reinforcement. It also became more exposed to railway loading. It was designed similarly to a bridge deck to Eurocode 2.
The design and reinforcement detailing accommodated unusual elements originally located in the FSC: track drainage, catchpits, undertrack crossing ducts and fire mains with tighter tolerances than normally applicable to secondary lining. The elements were installed with the reinforcement and cast into the invert. The fire main crossing was therefore procured and installed separately from the remaining pipeline. End details of cast-in elements were agreed with C610. The amalgamation moved the position of the PRD. A new system was provided between the FSC and SSC with end details connecting into the standard system.
The amalgamation moved the joint between invert and sprayed arch upwards, improving the structural efficiency of the arch and removing most reinforcement. The structures were neatly divided into cast RC without structural fibres and SCL without rebar.