Bookmark(0)

Published

10th April 2019

Knowledge Type

Case study Good Practice Document

Organisation

, Network Rail Ltd

Major Project

Thameslink Programme

Of Interest To

Academia Consultants Contractors Leadership teams Private sector clients Public sector clients

Thameslink Delivery and Execution Strategy

Summary

London Bridge Area Partnership partners worked in a uniquely close collaboration throughout to deliver 128 stages of construction since 2012, a staging plan that took over three years to perfect. This accommodated the re-signalling, track remodelling and construction of London Bridge station, construction of the Bermondsey Dive Under to the east and Borough Viaduct to the west – all while continuing to operate over 80 trains per hour alongside the construction sites. This staging strategy formed the blueprint for delivery; each stage of the programme created the next worksite for the station team, track team, civil engineering team or all three.